ISEB-PM1 practice question 27 of 35

You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:

Full set: 625 questions
Answer options
A: See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis Correct answer
B: Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation
C: Look for someone to blame before you see the sponsor
D: Do nothing until the slippage occurs
E: Immediately inform the sponsor and ask for advice
Correct Answer:
A. See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
Scroll to Top