LEED-AP-BDC practice question 31 of 35

In a large industrial or commercial building, which energy end uses are classified as systems composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering?

Full set: 305 questions
Answer options
A: HVAC air system for air conditioning
B: Electrical lighting system during peak use hours
C: Water flow system used for public faucets and toilets
D: Condenser water system with a cooling tower and condenser water pumps Correct answer
Correct Answer:
D. Condenser water system with a cooling tower and condenser water pumps
Explanation

The Advanced Energy Metering credit requires metering for all individual energy end uses that represent 10% or more of the total annual energy consumption. The credit intends to disaggregate the total building energy use into its major components. A condenser water system, which includes equipment like cooling towers (fans) and condenser water pumps, is a distinct, energy-intensive system in large commercial buildings. Metering this group of discrete but related equipment as a single end use is a standard and compliant approach for this credit, allowing for effective monitoring and management of that system's energy consumption.

Why Incorrect

A. "HVAC air system" is too general; the credit requires metering of specific end uses like fans, heating, or cooling, which might be part of this larger system.
B. Metering should capture the total consumption of the lighting system, not just its use during peak hours, to be compliant.
C. A water flow system for faucets and toilets measures water consumption, not energy consumption, and is therefore not relevant to this energy-focused credit.

References

1. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. "EA Credit: Advanced Energy Metering," pp. 381-384. The guide lists examples of end uses, including "HVAC pumps" and "HVAC heat rejection" (which includes cooling towers), and states that meters must be permanently installed and record at intervals of one hour or less.

2. ASHRAE. (2010). ASHRAE Guideline 14-2014: Measurement of Energy, Demand, and Water Savings. This guideline, often referenced in energy management, provides methodologies for measuring performance, which includes sub-metering distinct systems like condenser water loops.

Scroll to Top