LEED-AP-BDC practice question 32 of 35

Which of the following strategies is allowed under Energy Atmosphere Credit, Renewable Energy Production, and will help a project achieve Energy Atmosphere Credit, Optimize Energy Performance?

Full set: 305 questions
Answer options
A: Install an on-site photovoltaic array Correct answer
B: Purchase Green-e certified carbon offsets
C: Purchase Green-e certified Renewable Energy Certificates (RECs)
D: Install a ground-source heat pump
Correct Answer:
A. Install an on-site photovoltaic array
Explanation

Installing an on-site photovoltaic array is a strategy for the Energy and Atmosphere (EA) Credit, Renewable Energy Production. The energy generated by this on-site system reduces the building's net energy cost. This reduction in energy cost can be included in the proposed building performance model, directly contributing to the percentage of energy cost savings required for the EA Credit, Optimize Energy Performance. Off-site renewables and efficiency measures do not satisfy the requirements for both credits simultaneously.

Why Incorrect

B. Carbon offsets are an off-site strategy addressed by the Green Power and Carbon Offsets credit, not Optimize Energy Performance.
C. Renewable Energy Certificates (RECs) are an off-site procurement method and do not contribute to the Optimize Energy Performance credit calculation.
D. A ground-source heat pump is an energy efficiency measure that helps achieve Optimize Energy Performance but is not considered renewable energy production under that specific credit.

References

1. U.S. Green Building Council. (2021). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. Page 431, "EA Credit: Optimize Energy Performance," Step-by-Step Guidance, Step 5.

2. U.S. Green Building Council. (2021). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. Page 461, "EA Credit: Renewable Energy Production," Requirements.