LEED-AP-BDC practice question 18 of 35

The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve

Full set: 305 questions
Answer options
A: Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices Correct answer
B: Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 1. Raw Material Source and Extraction Reporting
C: Materials and Resources Credit, Building Product Disclosure and Optimization Environmental Product Declarations, Option 1. Environmental Product Declarations
D: Materials and Resources Credit, Construction and Demolition Waste Management, Option 1. Diversion
Correct Answer:
A. Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices
Explanation

The MR Credit "Building Product Disclosure and Optimization - Sourcing of Raw Materials" has two options. Option 2, "Leadership Extraction Practices," rewards the use of products that meet specific third-party verified standards. The LEED v4 Reference Guide explicitly lists products certified to the Sustainable Agriculture Network’s "Sustainable Agriculture Standard" as qualifying bio-based materials for this option. The product's cost ($80,000) would be valued at 100% and contribute toward the credit's threshold for achieving one point.

Why Incorrect

B. Option 1 is for reporting on raw material sources, not for using products with specific leadership certifications like the Sustainable Agriculture Standard.
C. This is a different credit (MRc2) that deals with Environmental Product Declarations (EPDs), which are based on life-cycle assessments, not sustainable sourcing practices.
D. This is a different credit (MRc5) focused on diverting construction waste from landfills, which is unrelated to the sourcing of new materials.

References

1. U.S. Green Building Council. (2019). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. "MR Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials," Option 2: Leadership Extraction Practices, p. 488.

2. U.S. Green Building Council. (2023). LEED v4.1 Building design and construction. "MR Credit: Sourcing of Raw Materials," Table 1. Multi-attribute criteria for products.