LEED-AP-IDC practice question 26 of 35

A tenant is targeting LEED Platinum certification and has hired a LEED AP Interior Design and Construction consultant to help identify and use opportunities to achieve synergies across disciplines and building systems. Which of the following analyses are required to be completed in the Integrated Process Worksheet to achieve an additional point?

Full set: 100 questions
Answer options
A: Water-Related Systems Correct answer
B: Energy-Related Systems Correct answer
C: Indoor Air Quality Systems
D: Waste Management Systems
Correct Answer:
A. Water-Related Systems; B. Energy-Related Systems
Explanation

LEED v4 ID+C awards the single Integrative Process point only when the team documents, in the LEED Online Integrative Process Worksheet, (1) a preliminary energy-related systems analysis and (2) a preliminary water-related systems analysis completed before schematic design and used to inform the Basis of Design. No other system analyses are mandated for this credit.

Why Incorrect

C. Indoor air-quality evaluation is addressed under EQ credits; it is not part of the Integrative Process Worksheet requirements.
D. Waste management planning belongs to MR credits and is not listed among the analyses required for the Integrative Process point.

References

1. USGBC. LEED v4 for Interior Design and Construction Reference Guide, “Integrative Process,” Requirements, pp. 48-50.

2. USGBC LEED Credit Library (ID+C v4). “Integrative Process,” ‘Step-by-Step Guidance,’ items 1 & 2, rev. 11-Jan-2021.

3. National Renewable Energy Laboratory, Torcellini P. et al. “Guidelines for Integrating Performance Analysis in the Design Process,” NREL/TP-550-38677, 2005, cited in LEED v4 ID+C RG p. 52.

4. MIT OpenCourseWare. Course 4.463 “Building Technology – Integrative Design,” Lecture 3: Energy & Water Interaction, 2016, slides 12-14.