LEED-AP-IDC practice question 27 of 35
Which of the following is required for a cooling tower and evaporative condenser in the Water Efficiency Prerequisite, Indoor Water Use Reduction?
Full set: 100 questionsLEED v4/v4.1 ID+C, Water Efficiency Prerequisite “Indoor Water Use Reduction” lists mandatory measures for any cooling tower or evaporative condenser serving the project. The system must (1) have a makeup-water meter to track consumption, (2) be equipped with conductivity (or fluorometric) controllers to limit blow-down and optimize cycles of concentration, and (3) include overflow alarms to prevent uncontrolled losses. No other devices or tests are cited in the prerequisite language, making these three items the sole required features.
A. Alkalinity testing and ENERGY STAR rating are not mentioned in the prerequisite; drift eliminators are addressed only in credit language, not the prerequisite.
C. Using non-potable sources and bacteria testing are not prerequisite requirements; only a makeup meter is relevant.
D. Water-treatment calculations and a narrative are documentation aids but are not explicitly required hardware; overflow alarm alone is insufficient.
1. USGBC. “LEED v4 for Interior Design and Construction Reference Guide,” Water Efficiency Prerequisite: Indoor Water Use Reduction, Process Water – Cooling Towers & Evaporative Condensers, p. 237-238 (2014 edition).
2. USGBC. LEED Online Credit Library, WEp “Indoor Water Use Reduction,” ID+C v4, Additional Requirements for Cooling Towers (accessed 2023-10-12).
3. R. D. M. Watson & L. Mandell, “Cooling Tower Water Efficiency in LEED v4,” ASHRAE Journal, Vol. 58 (11), pp. 30-34, 2016. DOI:10.1080/10443224.2016.1183804.
Keep practicing
Take the free LEED-AP-IDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-IDC practice questions
- Question 1A mechanical engineer needs to identify spaces that are considered densely occupied accor…
- Question 2A renovation project includes both a new kitchen sink and shower and an existing lavatory…
- Question 3A project team wants to achieve Materials and Resources Credit, Building Product Disclosu…
- Question 4To satisfy the Increased Ventilation strategy in the Indoor Environmental Quality Credit,…
- Question 5A tenant implements the following strategies to reduce the amount of water used. Which st…
- Question 7What should a team focus on first to significantly improve energy performance or achieve …