LEED-AP-IDC practice question 29 of 35

In addition to the basic requirements for Energy and Atmosphere, Fundamental Commissioning and Verification, which is required to achieve Energy and Atmosphere, Enhanced Commissioning, Option 1?

Full set: 100 questions
Answer options
A: Develop and implement a commissioning plan
B: Review the contractor's submittals for compliance with design documents Correct answer
C: Verify the installation and performance of the systems being commissioned
D: Review the owner's requirements and the basis of design for clarity and completeness
Correct Answer:
B. Review the contractor's submittals for compliance with design documents
Explanation

LEED v4 ID+C Energy & Atmosphere credit “Enhanced Commissioning—Option 1: Enhanced System Commissioning” adds tasks beyond the EA prerequisite “Fundamental Commissioning & Verification.” The first additional task listed in the credit requirements is to “review contractor submittals” to verify they meet the Owner’s Project Requirements and Basis of Design. Developing the Cx plan, OPR/BOD review, and verifying system installation are already mandatory under the prerequisite, so only the contractor-submittal review is new and therefore required specifically for Option 1.

Why Incorrect

A. Developing/implementing the commissioning plan is a prerequisite activity; not an extra requirement for Enhanced Commissioning.
C. Field verification of installation and performance is covered under Fundamental Commissioning and thus not unique to Option 1.
D. OPR and BOD review is fundamental-level work; Enhanced Commissioning presumes these are already complete.

References

1. USGBC. “LEED v4 Interior Design & Construction Reference Guide,” EA Credit: Enhanced Commissioning, Option 1, Requirements—bullet 1 “Review contractor submittals.” (2014 ed., p. 195-196).

2. USGBC. “LEED v4 Interior Design & Construction Reference Guide,” EA Prerequisite: Fundamental Commissioning & Verification, Requirements—items 1-4 (Cx plan, OPR/BOD review, installation verification, etc.). (2014 ed., p. 188-190).

3. ASHRAE Guideline 0-2013, Section 5.2.6 “Design Phase—Submittal Review” confirms submittal review as a distinct commissioning process step beyond basic plan development.