LEED-AP-IDC practice question 29 of 35
In addition to the basic requirements for Energy and Atmosphere, Fundamental Commissioning and Verification, which is required to achieve Energy and Atmosphere, Enhanced Commissioning, Option 1?
Full set: 100 questionsLEED v4 ID+C Energy & Atmosphere credit “Enhanced Commissioning—Option 1: Enhanced System Commissioning” adds tasks beyond the EA prerequisite “Fundamental Commissioning & Verification.” The first additional task listed in the credit requirements is to “review contractor submittals” to verify they meet the Owner’s Project Requirements and Basis of Design. Developing the Cx plan, OPR/BOD review, and verifying system installation are already mandatory under the prerequisite, so only the contractor-submittal review is new and therefore required specifically for Option 1.
A. Developing/implementing the commissioning plan is a prerequisite activity; not an extra requirement for Enhanced Commissioning.
C. Field verification of installation and performance is covered under Fundamental Commissioning and thus not unique to Option 1.
D. OPR and BOD review is fundamental-level work; Enhanced Commissioning presumes these are already complete.
1. USGBC. “LEED v4 Interior Design & Construction Reference Guide,” EA Credit: Enhanced Commissioning, Option 1, Requirements—bullet 1 “Review contractor submittals.” (2014 ed., p. 195-196).
2. USGBC. “LEED v4 Interior Design & Construction Reference Guide,” EA Prerequisite: Fundamental Commissioning & Verification, Requirements—items 1-4 (Cx plan, OPR/BOD review, installation verification, etc.). (2014 ed., p. 188-190).
3. ASHRAE Guideline 0-2013, Section 5.2.6 “Design Phase—Submittal Review” confirms submittal review as a distinct commissioning process step beyond basic plan development.
Keep practicing
Take the free LEED-AP-IDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-IDC practice questions
- Question 1A mechanical engineer needs to identify spaces that are considered densely occupied accor…
- Question 2A renovation project includes both a new kitchen sink and shower and an existing lavatory…
- Question 3A project team wants to achieve Materials and Resources Credit, Building Product Disclosu…
- Question 4To satisfy the Increased Ventilation strategy in the Indoor Environmental Quality Credit,…
- Question 5A tenant implements the following strategies to reduce the amount of water used. Which st…
- Question 7What should a team focus on first to significantly improve energy performance or achieve …
