LEED-AP-IDC practice question 30 of 35

Which of the following statements is correct when defining the project boundary?

Full set: 100 questions
Answer options
A: The project boundary must be defined by the limit of construction
B: The LEED project boundary cannot include more than one building
C: The gross floor area of the LEED project should be no less than 1,000 ft2 (93 m2)
D: Contiguous land that is associated with the project that is altered as a result of construction must be included Correct answer
Correct Answer:
D. Contiguous land that is associated with the project that is altered as a result of construction must be included
Explanation

LEED v4 Minimum Program Requirement 3 (MPR 3) states that the LEED project boundary “must include all contiguous land that is associated with the project and that is altered as a result of the project’s construction activity.” This directive applies across all rating systems, including Interior Design + Construction (ID+C). Therefore statement D is correct. The other statements misstate LEED rules: the boundary is not required to match the limit of construction exactly, a single LEED project may encompass more than one building under campus or group certification, and the minimum program area for ID+C projects is 250 ft², not 1,000 ft².

Why Incorrect

A. Boundary may differ from construction limits; ID+C projects often exclude exterior disturbance altogether.
B. Campus and group certifications allow one LEED boundary to include multiple buildings.
C. LEED v4 sets the minimum gross floor area for ID+C projects at 250 ft² (22 m²), not 1,000 ft².

References

1. U.S. Green Building Council. “LEED v4 Minimum Program Requirements,” MPR 3, sub-section “Site conditions to include,” p. 5 (Oct 2014 edition).

2. U.S. Green Building Council. LEED v4 for Interior Design and Construction Reference Guide, “Getting Started – Minimum Program Area,” Table 1, p. 15 (2014), minimum 250 ft².

3. U.S. Green Building Council. “LEED Campus Guidance,” v4, §2.3 “Group Certification,” pp. 6-7, allowing multiple buildings within one LEED boundary.