LEED-AP-IDC practice question 18 of 35
The site of a new open-plan office building is located near a highway. The acoustic consultant is investigating the possibility of using sound masking system to cover the noise impact from the busy road. If sound masking is found to be a feasible option, the noise design of the project can have a maximum limit up to
Full set: 100 questionsLEED v4 ID+C EQ Credit “Acoustic Performance” adopts the background-noise limits in ANSI/ASA S12.2 and the ASHRAE Applications Handbook. For open-plan office areas, two limits are given:
• without sound masking: ≤ 35 dBA (or NC-35)
• with a designed electronic sound-masking system: ≤ 48 dBA (or NC-45). Because the consultant is specifically considering a sound-masking system, the design may rise to—but must not exceed—48 dBA. This value maintains speech privacy while preventing excessive overall noise and is the highest level permitted by the referenced standards and by the LEED credit language.
A. 36 dBA – applies to open offices that do NOT employ sound masking; too low for masked design.
C. 62 dBA – exceeds ANSI/ASA and LEED limits; would compromise comfort and fail the credit.
D. 70 dBA – far above any accepted indoor background-noise criterion; clearly non-compliant.
1. USGBC. LEED v4 for Interior Design + Construction Reference Guide, EQ Credit Acoustic Performance, Table 1 “Maximum Background Sound-Pressure Levels,” p. 662 (limit: 48 dBA with masking).
2. ANSI/ASA S12.2-2008 (R2013) “Criteria for Evaluating Room Noise,” Table 3, Open-plan offices with sound masking – RC/NC 45 ≈ 48 dBA.
3. ASHRAE HVAC Applications Handbook 2019, Ch. 48 “Sound and Vibration,” Table 1, “Recommended Design Criteria for Background Sound,” open offices with masking: 45 NC ≈ 48 dBA.
Keep practicing
Take the free LEED-AP-IDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-IDC practice questions
- Question 1A mechanical engineer needs to identify spaces that are considered densely occupied accor…
- Question 2A renovation project includes both a new kitchen sink and shower and an existing lavatory…
- Question 3A project team wants to achieve Materials and Resources Credit, Building Product Disclosu…
- Question 4To satisfy the Increased Ventilation strategy in the Indoor Environmental Quality Credit,…
- Question 5A tenant implements the following strategies to reduce the amount of water used. Which st…
- Question 7What should a team focus on first to significantly improve energy performance or achieve …