MSP-FOUNDATION practice question 21 of 25

Which of these is a focus of the ‘embed the outcomes’ process?

Full set: 117 questions
Answer options
A: To control the work required to manage each tranche of delivery
B: To maintain an acceptable balance between delivery, transition, realization of benefits, and affordability
C: To identify when the work has been completed as planned
D: To realize and measure benefits Correct answer
Correct Answer:
D. To realize and measure benefits
Explanation

The 'Embed the outcomes' process is a critical part of the MSP transformational flow. Its primary purpose is to integrate the new capabilities delivered by the programme's projects into business-as-usual (BAU) operations. This integration is what enables the desired outcomes to be achieved. A central focus of this process is, therefore, to ensure that the planned benefits are actually realized and to measure their achievement against the benefits realization plan. This confirms the programme is delivering its intended value.

Why Incorrect

A. This describes the purpose of the ‘Manage the tranches’ process, which is responsible for overseeing and controlling the delivery of projects within each tranche.
B. This is a core responsibility of the Programme Board, a governance body, which ensures the overall viability and alignment of the programme throughout its lifecycle.
C. This is an activity associated with project closure or the ‘Close the programme’ process, which confirms that deliverables have been completed as specified.

References

AXELOS. (2020). Managing Successful Programmes (MSP) 5th Edition. TSO (The Stationery Office).

Section 10.6, 'Embed the outcomes': The purpose is stated as: "to integrate the outputs of the programme into business-as-usual (BAU), enabling the realization of benefits." This section details activities such as measuring benefits and assessing the achievement of outcomes, directly supporting option D.

Section 10.5, 'Manage the tranches': The purpose is described as "to direct the work to be undertaken within a tranche", which aligns with the incorrect option A.

Chapter 7, 'Governance': This chapter outlines the responsibilities of the Programme Board, including maintaining the balance described in option B.

Section 10.7, 'Close the programme': This process includes activities to "confirm that all the work planned for the programme has been completed," which relates to option C.