MSP-PRACTITIONER practice question 14 of 15
Which of the following is a KEY attribute for a Programme Manager?
Full set: 75 questionsMSP defines a Programme Manager as the individual who plans, monitors and controls the coordinated delivery of projects. A core attribute listed for this role is “good knowledge of programme and project-management approaches (e.g. MSP, PRINCE2).” This competency enables the Programme Manager to advise project teams and integrate their outputs into programme outcomes, therefore it is singled out as a key attribute.
A. Ongoing operational duties typify the Business Change Manager, not the full-time Programme Manager.
B. Change-management expertise is explicitly required for Business Change Managers; it is desirable but not stated as “key” for Programme Managers.
D. Direct access to senior stakeholders is a primary requirement for the Senior Responsible Owner (SRO), not the Programme Manager.
1. AXELOS
“Managing Successful Programmes (MSP)”
5th Ed.
TSO
2020
Sec. 4.6.5 Programme Manager – Key attributes
bullet 3
p. 155.
2. AXELOS
“Managing Successful Programmes (MSP)”
2011 Ed.
Appendix B – Role descriptions
Programme Manager
bullet “good knowledge of project-management approaches”
p. 242.
Keep practicing
Take the free MSP-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other MSP-PRACTITIONER practice questions
- Question 1Which of the following will not be in Issue register?
- Question 2Select the best option defined by following sentence: 'Action of carrying out the coordin…
- Question 3Through which document programmes establish the context in which risks will be identified…
- Question 4For a programme that focuses on Political and societal change which scenario will lead to…
- Question 5Which of the following is not an Input to delivering the capability?
- Question 6Which of the following statements best defines 'transformational Flow'?