PGMP practice question 16 of 35

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The…

Choose your answer, then check it against the explanation.

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
Answer options
Question 16 of 35

Keep practicing

Take the free PGMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PGMP practice questions

Scroll to Top