PGMP practice question 18 of 35
A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released…
Full set: 452 questionsAccording to the PMI Standard for Program Management, a critical activity within the Program Closure Phase is the formal transition of the program's outputs and benefits to the sustaining organization, which is typically the operations department. The program manager's responsibility is to ensure that a comprehensive transition plan is executed. This plan must include knowledge transfer, documentation, and processes for ongoing support to guarantee that the benefits delivered by the program (the Alpha software) can be sustained post-closure. This directly addresses the sponsor's concern about long-term support.
B. Keep the Alpha program open until support is no longer required, then execute program closure. Programs are temporary endeavors with defined start and end dates. Ongoing support is an operational function, and keeping a program open indefinitely for this purpose violates fundamental program management principles.
C. Adjust Alpha’s exit criteria to ensure its support is included in the Beta program. This is incorrect because the responsibility for sustaining the benefits of one program should not be transferred to another new, temporary program. Operational support for Alpha is an operational function, not a component of the Beta development program.
D. Document the program closure procedure to ensure that resources are released from Alpha to develop Beta. While releasing resources is a part of program closure, this action focuses on administrative closure and resource allocation. It does not address the sponsor's specific concern regarding the ongoing support and sustainment of the Alpha software.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.).
Section 5.5
Program Transition and Closure: This section states
"This domain involves the activities performed to transition the program benefits to the sustaining organization and formally close the program." (p. 89). This supports the idea that transition to a sustaining entity (operations) is the correct procedure.
Section 3.5.5
Program Closure Phase: This section details the activities of the phase
including
"During this phase
program managers are responsible for... finalizing the transition of benefits to the sustaining organization
and ensuring that benefit sustainment plans are in place and are being executed by the sustaining organization." (p. 41). This directly aligns with option A.
2. Thiry
M. (2015). A Framework for Value Management Practice. In Program Management: A Life Cycle Approach (pp. 1-23). John Wiley & Sons
Inc.
This academic text emphasizes that program closure involves a structured handover to ensure benefits are sustained. It states
"The program closure is not the end of the benefits; it is the moment when the business takes over the sustainment of the benefits." This reinforces that responsibility shifts to the business/operations
not another program.
Keep practicing
Take the free PGMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PGMP practice questions
- Question 1You are the program manager of the NHQ Program. You will need to initiate six projects fo…
- Question 2All of the following are resources that you will need to monitor and control in a program…
- Question 3A company is evaluating the implementation of enterprise resource planning (ERP) software…
- Question 4The program manager defines the program objectives, requirements, and develops a high-lev…
- Question 5Which of the following represents the duration of activities against a calendar?
- Question 6During the selection of source process, you assign certain points towards various categor…