PGMP practice question 19 of 35
The program manager of a multinational program must reconcile data including subject matter experts’ labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis. Which of the following should be considered to get a baseline budget?
Full set: 452 questionsThe program budget baseline is established by aggregating the detailed cost estimates from all its components, including projects, sub-programs, and other program-level activities. The act of reconciling labor and resource hour estimates is a fundamental step in developing these component cost estimates. These estimates serve as the primary input for determining the overall program budget, which is then time-phased according to the schedule to create the cost baseline and facilitate cash flow analysis.
A. Currency exchange rates are a financial risk factor applied to cost estimates in a multinational program, not the foundational input for the budget itself.
C. The baseline schedule is critical for time-phasing the budget and for cash flow planning, but it does not provide the actual cost figures.
D. Program payment schedules are an output of financial planning that dictates cash outflow timing; they do not determine the budget's total value.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.4.2, Program Budgeting, p. 78. The standard states, "The program budget is developed by aggregating the estimated costs of individual program components along with any other costs associated with the integration and management of the program." This directly supports that component cost estimates are the primary input.
2. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Figure 5-5, Program Financial Management Activities, p. 74. This figure clearly depicts "Estimate Costs" as a preceding activity and input to "Determine Budget," reinforcing that cost estimates are foundational to creating the budget.
Keep practicing
Take the free PGMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PGMP practice questions
- Question 1You are the program manager of the NHQ Program. You will need to initiate six projects fo…
- Question 2All of the following are resources that you will need to monitor and control in a program…
- Question 3A company is evaluating the implementation of enterprise resource planning (ERP) software…
- Question 4The program manager defines the program objectives, requirements, and develops a high-lev…
- Question 5Which of the following represents the duration of activities against a calendar?
- Question 6During the selection of source process, you assign certain points towards various categor…