PMI-ACP practice question 16 of 35
A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated. Is this agile strategy appropriate?
Full set: 482 questionsAgile gains speed through short feedback loops and continuous integration. Developing all three components separately and postponing testing/integration eliminates iterative feedback, greatly increasing integration risk and delaying discovery of defects—contradicting agile principles.
A. Parallel component work without integration is sequential, not agile, and hampers feedback.
B. Hybrid label doesn’t mitigate lost feedback and late integration risk.
C. Communication loss is possible but root problem is missing feedback/integration.
1. PMI Agile Practice Guide, 2017, §6.3 “Deliver Frequently & Integrate Continuously,” p. 93.
2. Scrum Guide 2020, “Empirical Process Control,” lines 25-31.
3. Larman, C. & Vodde, B. “Large-Scale Scrum,” 2017, Ch. 5, pp. 102-103 (peer-reviewed).
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …