An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to…
Full set: 482 questionsWith a fixed, externally imposed delivery date, agile recommends keeping time and cost constant while varying scope. Reducing release scope allows the team to deliver the highest-value features with the diminished velocity, satisfying the fair deadline without jeopardising quality.
B. “As many features as possible” lacks prioritisation and risks stakeholder dissatisfaction if key items are omitted.
C. Extending the timeline contradicts the immovable market event and executive mandate.
D. Hiring now adds onboarding overhead; new staff would not offset the immediate 30 % velocity loss in time.
1. Project Management Institute. “Agile Practice Guide.” 2017, §3.2, p. 17 – Fix time & cost, adjust scope.
2. Cohn, M. “Agile Estimating and Planning.” Prentice Hall, 2006, Ch. 14 – Release planning around fixed dates by trimming scope.
3. Williams, L. “What Agile Teams Think of Agile Principles.” IEEE Software, 29(4), 2012, p. 72 – Market-driven releases favour scope negotiation over deadline change.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …