PMI-ACP practice question 8 of 35
A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?
Full set: 482 questionsAgile adoption succeeds when everyone affected understands and supports the change. PMI’s Agile Practice Guide states that introducing agile “requires broad‐based training and coaching so that teams, managers, and stakeholders share a common understanding of agile values, principles, and practices.” Organising workshops for all stakeholders therefore gives predictive-oriented teams the knowledge, vocabulary and mindset they need before roles or artefacts are assigned, ensuring a consistent, organisation-wide shift to agile delivery.
A. Limits training to predefined roles; fails to create the whole-system understanding that PMI prescribes for successful adoption.
C. Focusing only on senior leaders ignores the delivery teams that must execute the work.
D. Mixing agile and predictive on the same product fractures process consistency and inhibits learning for the formerly predictive team.
1. PMI. Agile Practice Guide
2017
Section 2.2 “Implementing Agile on a Project”
pp. 19-20.
2. Dikert
K.
Paasivaara
M.
& Lassenius
C. “Challenges and success factors for large-scale agile transformations.” Journal of Systems and Software 119 (2016): 87-108. https://doi.org/10.1016/j.jss.2016.06.013.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …