PMI-ACP practice question 7 of 35
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity…
Full set: 482 questionsBoth teams have estimated 14 sprints to complete their respective projects (Team A: 420÷30=14; Team B: 280÷20=14). While they use different story point scales, the relative sizing within each team results in the same project duration estimate. Story points are relative units specific to each team, not absolute measurements. The key insight is that both teams perceive their projects will require the same number of iterations to complete.
A. Team B's lower story points don't indicate underestimation since story points are team-specific relative measures, not absolute values.
B. Velocity confidence cannot be determined from these estimates alone; the numbers only show each team's baseline velocity.
C. Technology details are not required for story point estimation as they're already factored into team-specific estimates.
3. References:
1. Cohn, M. (2005). Agile Estimating and Planning. Chapter 4: "Estimating Size with Story Points," pp. 35-38. Prentice Hall PTR.
2. Rubin, K. (2012). Essential Scrum: A Practical Guide to the Most Popular Agile Process. Chapter 7: "Estimation and Velocity," pp. 129-134. Addison-Wesley.
3. Sutherland, J. & Schwaber, K. (2017). The Scrum Guide. Section: "Development Team," pp. 7-8. Available at: https://scrumguides.org/docs/scrumguide/v2017/2017-Scrum-Guide-US.pdf
4. Larman, C. & Vodde, B. (2010). Practices for Scaling Lean & Agile Development. Chapter 5: "Feature Teams," pp. 89-92. Addison-Wesley.
5. IEEE Computer Society (2014). Guide to the Software Engineering Body of Knowledge (SWEBOK) V3.0. Chapter 6: "Software Construction," Section 6.3.4. Available at: https://www.computer.org/education/bodies-of-knowledge/software-engineering
1. PMI & Agile Alliance. “Agile Practice Guide” (2017)
§4.3.2
pp. 46-47 – points unique to a team
non-comparable.
2. PMI & Agile Alliance. “Agile Practice Guide” (2017)
§4.3.4
p. 50 – velocity used to forecast number of iterations.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …