PMI-ACP practice question 7 of 35
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity…
Choose your answer, then check it against the explanation.
Two teams have received project requirements and completed estimates. Team A estimates 420
story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points
for scope and 20 story points for velocity per sprint. Both teams have same number of team
members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?
Question 7 of 35
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …