An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background. What should be considered when selecting the team?
Full set: 482 questionsScrum teams should be cross-functional and have a blend of deep expertise and broad, “T-shaped” skills so they can deliver end-to-end value. Selecting a balanced mix of specialists and generalists and arranging training keeps the team adaptable and self-sufficient for the website redesign.
A. Past conflict records alone are a poor proxy for present collaboration ability and diversity of skill.
C. Co-location is beneficial but not mandatory and may exclude needed talent.
D. Picking only prior high-velocity individuals ignores the need for complementary, cross-functional skills.
1. PMI, “Agile Practice Guide”, 2017, §6.4 Building High-Performing Teams; Exhibit 6-3 (T-shaped skills).
2. Schwaber & Sutherland, “The Scrum Guide”, 2020, Scrum Team—Cross-functional and self-managing.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …