PMI-ACP practice question 12 of 35
A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?
Full set: 482 questionsVelocity is an empirical measure that can only be learned by observing how much work a specific team actually completes in several real Sprints. A brand-new Scrum team therefore needs to run a few Sprints, measure completed story points, and then use the resulting average as its forecast for future Sprints. Any attempt to predetermine velocity without data contradicts the empirical-process control that underpins Scrum.
A. Borrowing another project’s velocity ignores the principle that each team’s capacity is unique.
B. Averaging members’ guesses substitutes speculation for empirical measurement.
C. Velocity supplied by a sponsor is external, not evidence-based, and risks over-commitment.
1. PMI
“Agile Practice Guide”
2017
§5.3.1 Velocity
p.58.
2. Scrum Guide 2020
“Sprint Planning—Forecasting Work”
p.10; empirical basis for forecasting.
3. MIT OpenCourseWare
15.S12 “Agile Methods”
Lecture 4 slides
“Velocity emerges after several iterations”
slide 12.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …