PMI-ACP practice question 12 of 35

A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?

Full set: 482 questions
Answer options
A: Engage the team to determine the sprint velocity based on previous agile projects.
B: Average the sprint velocity based on input from team members
C: Share the sprint velocity obtained from the sponsor with the team
D: Run multiple sprints before determining the sprint velocity with the team. Correct answer
Correct Answer:
D. Run multiple sprints before determining the sprint velocity with the team.
Explanation

Velocity is an empirical measure that can only be learned by observing how much work a specific team actually completes in several real Sprints. A brand-new Scrum team therefore needs to run a few Sprints, measure completed story points, and then use the resulting average as its forecast for future Sprints. Any attempt to predetermine velocity without data contradicts the empirical-process control that underpins Scrum.

Why Incorrect

A. Borrowing another project’s velocity ignores the principle that each team’s capacity is unique.
B. Averaging members’ guesses substitutes speculation for empirical measurement.
C. Velocity supplied by a sponsor is external, not evidence-based, and risks over-commitment.

References

1. PMI

“Agile Practice Guide”

2017

§5.3.1 Velocity

p.58.

2. Scrum Guide 2020

“Sprint Planning—Forecasting Work”

p.10; empirical basis for forecasting.

3. MIT OpenCourseWare

15.S12 “Agile Methods”

Lecture 4 slides

“Velocity emerges after several iterations”

slide 12.