PMI-ACP practice question 11 of 35
A project team realizes that an important task on the iteration backlog will take more time than originally estimated What should the project team do?
Full set: 482 questionsA core principle of agile development, particularly in Scrum, is the use of fixed-length iterations (time-boxing). If a task is larger than estimated and cannot be completed within the iteration without jeopardizing the sprint goal or the time-box, it should not be continued indefinitely. The team should raise this issue, typically during a daily stand-up. After discussing with the Product Owner, the appropriate action is often to stop work on the item and move it back to the product backlog for re-estimation and re-prioritization in a future iteration.
A. Continuing to work breaks the time-box, a fundamental rule of iterations/sprints, which disrupts the project's rhythm and predictability.
B. Removing a team member is a punitive and counterproductive action that damages team morale and psychological safety.
C. Adding resources mid-sprint often disrupts the team and can slow down progress further, as described by Brooks's Law.
1. Project Management Institute & Agile Alliance. (2017). Agile Practice Guide. Project Management Institute. Section 5.2.5, p. 51. "The team may not be able to get all the work they planned for the timebox, but they can get the work that they did finish to a done state."
2. Schwaber, K., & Sutherland, J. (2020). The 2020 Scrum Guide. Scrum.org. p. 9. "Sprints are fixed length events... No changes are made that would endanger the Sprint Goal."
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …
