PMI-CAPM practice question 31 of 35

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Full set: 1,329 questions
Answer options
A: Plan Stakeholder Management
B: Identify Stakeholders Correct answer
C: Manage Stakeholder Engagement
D: Control Stakeholder Engagement
Correct Answer:
B. Identify Stakeholders
Explanation

The Identify Stakeholders process is the fundamental step for discovering all individuals, groups, or organizations that could impact or be impacted by the project. A key activity within this process is to analyze and document their requirements, expectations, and interests. If a stakeholder expresses a need previously unknown to the project manager, it signifies a gap in this initial identification and analysis. The primary output of this process, the stakeholder register, should have captured this need. A failure at this stage directly leads to an incomplete understanding that affects all subsequent stakeholder management activities.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 13.1

Identify Stakeholders. Newtown Square

PA: Project Management Institute.

Page 507: "Identify Stakeholders is the process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests

involvement

interdependencies

influence

and potential impact on project success." This highlights that analysis of interests (needs) is core to this process.

Page 513: The description of the Stakeholder Register

the key output of Identify Stakeholders

explicitly lists "Stakeholder requirements" as a component. Missing a need is a direct failure to populate this document correctly.

2. MIT OpenCourseWare. (2012). 16.852J / ESD.352J Project Management

Fall 2012. Lecture 4: Stakeholder Management. Massachusetts Institute of Technology.

The lecture materials emphasize that the initial phase of stakeholder management involves answering "who are the stakeholders?" and "what are their interests/rights?". An incomplete answer to these questions during the identification phase is cited as a primary reason for unexpected issues and needs arising later in the project.