PMI-CAPM practice question 8 of 35
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of…
Choose your answer, then check it against the explanation.
The risk management team of a software project has decided that due to the lack of adequate talent
in the company, development of a specific part of the system is under high risk, so the team has
decided to outsource it. This is an example of which risk response?
Question 8 of 35
Keep practicing
Take the free PMI-CAPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-CAPM practice questions
- Question 1An input to the Estimate Activity Resources process is:
- Question 2When can pre-assignment of project team members occur?
- Question 3Which tool or technique of Plan Quality involves comparing actual or planned practices to…
- Question 4A project lifecycle is defined as:
- Question 5Change request status updates are an output of which process?
- Question 6What type of reward can hurt team cohesiveness?