PMI-CAPM practice question 8 of 35

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of…

Choose your answer, then check it against the explanation.

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
Answer options
Question 8 of 35

Keep practicing

Take the free PMI-CAPM practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-CAPM practice questions

Scroll to Top