PMI-CAPM practice question 9 of 35
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Full set: 1,329 questionsThe Procurement Statement of Work (SOW) is a formal document that provides a narrative description of the products, services, or results to be supplied under a contract. It is specifically developed from the project scope baseline, which includes the WBS, WBS dictionary, and project scope statement. The SOW's purpose is to define only the specific portion of the project's scope that will be performed by a seller. This ensures that potential sellers have a clear, complete, and concise understanding of the work required, allowing them to determine if they can meet the requirements and to prepare an appropriate response.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 12.1.3.1
Procurement Statement of Work. Newtown Square
PA: Project Management Institute. "The statement of work (SOW) for each procurement is developed from the project scope baseline and defines only that portion of the project scope that is to be included within the related contract."
2. MIT OpenCourseWare. (2012). ESD.36J System Project Management
Lecture 11: Project Execution: Procurement & Contracts. Massachusetts Institute of Technology. This courseware explains that the SOW is a critical procurement document that details the specific work to be performed by a contractor
derived from the project's overall requirements and scope.
Keep practicing
Take the free PMI-CAPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-CAPM practice questions
- Question 1An input to the Estimate Activity Resources process is:
- Question 2When can pre-assignment of project team members occur?
- Question 3Which tool or technique of Plan Quality involves comparing actual or planned practices to…
- Question 4A project lifecycle is defined as:
- Question 5Change request status updates are an output of which process?
- Question 6What type of reward can hurt team cohesiveness?