PMI-CAPM practice question 33 of 35
Which is an example of Administer Procurements?
Full set: 1,329 questionsAdminister Procurements (known as Control Procurements in the PMBOK® Guide – Sixth Edition) is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections as required. A key activity within this process is ensuring the seller performs according to the contract. Authorizing the contractor's work to proceed as specified in the contract is a fundamental part of managing and directing the seller's performance during the project execution and monitoring phases. This action confirms that the project is ready for the seller to begin a specific part of the work, thereby administering the contract terms.
1. Project Management Institute. (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition. Section 12.3, Administer Procurements, p. 377. The guide states this process includes "managing the procurement relationship and monitoring contract performance," which encompasses directing and authorizing the seller's work.
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 12.2, Conduct Procurements, p. 482. This section details that activities like negotiation and contract finalization occur here, distinguishing it from contract administration.
3. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 12.1, Plan Procurement Management, p. 474. This section lists procurement statement of work and source selection criteria as outputs, confirming these are planning activities.
4. Gubi, E. (2012). Project Procurement Management: A Guide to Effective Project-oriented Procurement. DTU Management Engineering. Technical University of Denmark. Report DTU-MAN-ME-2012-01, p. 21. The document describes contract administration as including "monitoring of the supplier’s performance, inspection and verification of deliverables, control of changes, and authorization of payments," which aligns with authorizing work.
Keep practicing
Take the free PMI-CAPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-CAPM practice questions
- Question 1An input to the Estimate Activity Resources process is:
- Question 2When can pre-assignment of project team members occur?
- Question 3Which tool or technique of Plan Quality involves comparing actual or planned practices to…
- Question 4A project lifecycle is defined as:
- Question 5Change request status updates are an output of which process?
- Question 6What type of reward can hurt team cohesiveness?