PMI-RMP practice question 7 of 35

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project. How could the risk manager have avoided the board's response?

Full set: 264 questions
Answer options
A: Engaging the key stakeholders during the prioritization process Correct answer
B: Prioritizing the risks based on the project sponsor's risk appetite
C: Engaging with the project sponsor before presenting to the board
D: Working with an established industry standard prioritization method
Correct Answer:
A. Engaging the key stakeholders during the prioritization process
Explanation

The fundamental issue described is a misalignment between the risk presentation format and the expectations of a key stakeholder group (the board). This indicates a failure to properly define and agree upon the risk management approach during the planning phase. Engaging key stakeholders, including the board or their representatives, during the process of defining risk categories, probability and impact scales, and prioritization rules is a critical step in the Plan Risk Management process. This collaborative approach ensures that the methodology for sorting and presenting risks is understood and accepted by those who will use the information for decision-making, thereby preventing such costly rework and delays.

Why Incorrect

B. Prioritizing based solely on the sponsor's risk appetite is insufficient, as it neglects the potentially different perspectives and requirements of other key stakeholders, such as the board.
C. While engaging the sponsor is a good practice, it does not guarantee alignment with the board, which is a distinct and powerful stakeholder group with its own requirements.
D. Using an industry standard does not guarantee acceptance. The risk management approach must be tailored to the specific project context and its unique stakeholder needs and preferences.

References

1. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.

Section 4.2.3.1, Risk Management Strategy: States that the risk management strategy should be "appropriate for the project and agreed to by key stakeholders." The prioritization method is a core component of this strategy.

Section 4.2.3.2, Stakeholder Risk Attitudes: Emphasizes that the risk management plan should document the risk attitudes of key stakeholders, as these attitudes "influence how risk management will be performed." This directly supports engaging stakeholders to understand their preferences for how risks are categorized and prioritized.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition.

Section 11.1, Plan Risk Management: This process is about defining how to conduct risk management activities. The inputs include the Stakeholder Register and Stakeholder Engagement Plan, highlighting the necessity of involving stakeholders from the outset to define the framework, including prioritization rules, which are documented in the resulting Risk Management Plan.

3. Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240.

This paper discusses the importance of tailoring the risk process, including the definition of scales and thresholds, to be meaningful and useful for the organization and its stakeholders. This supports the idea that a pre-defined or standard approach (Option D) may not be sufficient without stakeholder consultation and agreement. (https://doi.org/10.1016/S0263-7863(01)00074-6)