PMI-RMP practice question 6 of 35
An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?
Full set: 264 questionsThe identified issues of declining morale, mistrust, and isolation are indicators of a dysfunctional team culture and a breakdown in collaboration. In an agile environment, the project manager acts as a servant leader, responsible for fostering a cohesive and high-performing team. Promoting cross-training and mentoring directly addresses the root causes by encouraging team members to interact, share knowledge, and rely on one another. This builds interpersonal trust, breaks down silos, and fosters a sense of collective ownership and shared purpose. These activities are fundamental to creating the psychological safety and collaborative spirit necessary for a productive and cohesive agile team.
A. Introducing performance standards and evaluation methods can increase individual pressure and competition, potentially worsening mistrust and isolation in an already struggling team.
B. Clarifying project goals and contract constraints addresses project direction, not the underlying interpersonal and cultural issues causing low morale and mistrust.
D. A reward system based on position and experience promotes hierarchy and individual status, which is contrary to the collaborative, team-oriented ethos of agile methodologies.
1. Project Management Institute. (2017). Agile Practice Guide.
Section 5.2.2, T-shaped Skills, p. 43: The guide states, "Cross-functional team members seek to be T-skilled... Cross-training, pair work, and swarming facilitate better collaboration." This directly supports cross-training as a method to improve collaboration, which is at the heart of solving the team's issues.
Section 5.3, Servant Leadership, p. 49: Servant leadership emphasizes "facilitating collaboration" and "building a culture of trust." The actions in option C are prime examples of a servant leader facilitating collaboration and trust-building within the team.
2. Project Management Institute. (2019). The Practice Standard for Project Risk Management.
Section 3.2.2, Sources of Overall Project Risk, p. 19: This section notes that project complexity arising from "human behavior" is a source of risk. The declining morale and mistrust represent a significant human-behavior risk. Implementing a response like cross-training mitigates the risk of team failure.
3. Moe, N. B., Dingsøyr, T., & Dybå, T. (2010). A teamwork model for understanding an agile team: A case study of a Scrum project. Information and Software Technology, 52(5), 480-491. https://doi.org/10.1016/j.infsof.2009.11.004
This study emphasizes that shared knowledge and mutual support are critical for agile team effectiveness. The paper's findings support that practices like mentoring and knowledge sharing (inherent in cross-training) are essential for building the coordination and cohesion needed for high performance, directly addressing the problems of mistrust and isolation.
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…
- Question 8During a risk identification process in a construction project, the lack of space to inst…