PMI-RMP practice question 8 of 35

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact…

Choose your answer, then check it against the explanation.

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?
Answer options
Question 8 of 35

Keep practicing

Take the free PMI-RMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-RMP practice questions

Scroll to Top