An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project
Full set: 264 questionsThe scenario describes an emergent opportunity for one project (Project B) that arises from a risk response action in another (Project A). The most appropriate and immediate action for Project A's risk manager is to communicate this finding to the relevant stakeholder, which is the risk manager for Project B. This facilitates integrated risk management across projects, ensuring that organizational benefits are maximized. Consulting allows for the validation of the opportunity and the exploration of synergies, where both projects might coordinate their plans for mutual benefit. This proactive communication is a core responsibility of a risk manager operating within a multi-project environment.
A. This action is premature as Project A is still in execution, not closure. It also escalates an immediate tactical opportunity into a long-term strategic process change.
C. Combining entire risk registers is an inefficient and overly bureaucratic response to a single, specific cross-project opportunity. Direct communication is more effective.
D. This option demonstrates a siloed approach by focusing only on Project A and completely ignoring the identified opportunity that could benefit Project B and the organization.
1. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.
Section 4.5, Program Risk Management (p. 63): This section emphasizes that program risk management involves managing risks at a level above individual projects, including "the processes of identifying, analyzing, and planning responses to risks... and aggregating and managing component-level risks." This principle directly supports the need for communication and coordination between projects (components) like A and B to manage cross-cutting issues.
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition.
Section 11.6, Implement Risk Responses (p. 453): This process notes that implementing risk responses can result in secondary risks (or opportunities). The outputs include updates to the risk register and other project documents. The implicit next step for a risk affecting another project is communication, a fundamental theme of Project Integration Management (Chapter 4).
3. Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240.
DOI: https://doi.org/10.1016/S0263-7863(01)00074-600074-6)
This paper argues for a proactive approach to managing opportunities with the same rigor as threats. It states, "The aim of the opportunity management process is to... maximize their probability and/or impact." In the given scenario, ignoring the opportunity for Project B (Option D) or delaying action (Option A) would violate this principle. The first step to maximizing the opportunity is to engage the project that can exploit it (Option B).
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6An agile project manager has noticed their team's declining morale, mistrust, and isolati…
- Question 7After presenting a list of risks to the major project stakeholders and project sponsor, t…