PMI-RMP practice question 9 of 35

An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project

Full set: 264 questions
Answer options
A: While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B. Which action should the risk manager for Project A take?
B: Review the findings in Project A's closure documents and propose a new organizational process for portfolio risk management. Correct answer
C: Consult with Project B's risk manager and determine where synergies might exist between the risk management plans for both projects.
D: Combine the risk registers for Project A and Project B and determine if there are any additional cross-project opportunities to exploit.
E: Continue executing the planned risk mitigation to avoid any additional schedule impact to Project
F:
Correct Answer:
B. Review the findings in Project A's closure documents and propose a new organizational process for portfolio risk management.
Explanation

The scenario describes an emergent opportunity for one project (Project B) that arises from a risk response action in another (Project A). The most appropriate and immediate action for Project A's risk manager is to communicate this finding to the relevant stakeholder, which is the risk manager for Project B. This facilitates integrated risk management across projects, ensuring that organizational benefits are maximized. Consulting allows for the validation of the opportunity and the exploration of synergies, where both projects might coordinate their plans for mutual benefit. This proactive communication is a core responsibility of a risk manager operating within a multi-project environment.

Why Incorrect

A. This action is premature as Project A is still in execution, not closure. It also escalates an immediate tactical opportunity into a long-term strategic process change.
C. Combining entire risk registers is an inefficient and overly bureaucratic response to a single, specific cross-project opportunity. Direct communication is more effective.
D. This option demonstrates a siloed approach by focusing only on Project A and completely ignoring the identified opportunity that could benefit Project B and the organization.

References

1. Project Management Institute. (2019). The Standard for Risk Management in Portfolios, Programs, and Projects.

Section 4.5, Program Risk Management (p. 63): This section emphasizes that program risk management involves managing risks at a level above individual projects, including "the processes of identifying, analyzing, and planning responses to risks... and aggregating and managing component-level risks." This principle directly supports the need for communication and coordination between projects (components) like A and B to manage cross-cutting issues.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition.

Section 11.6, Implement Risk Responses (p. 453): This process notes that implementing risk responses can result in secondary risks (or opportunities). The outputs include updates to the risk register and other project documents. The implicit next step for a risk affecting another project is communication, a fundamental theme of Project Integration Management (Chapter 4).

3. Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240.

DOI: https://doi.org/10.1016/S0263-7863(01)00074-600074-6)

This paper argues for a proactive approach to managing opportunities with the same rigor as threats. It states, "The aim of the opportunity management process is to... maximize their probability and/or impact." In the given scenario, ignoring the opportunity for Project B (Option D) or delaying action (Option A) would violate this principle. The first step to maximizing the opportunity is to engage the project that can exploit it (Option B).