PMI-RMP practice question 10 of 35
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this…
Choose your answer, then check it against the explanation.
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact
their team. The stakeholder insists that this particular risk should be
mitigated to the greatest extent possible, however, the majority of other stakeholders feel that
different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
Question 10 of 35
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 3A project lihat was in the execution phase for the last six months was put on hold and wa…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6A risk management professional is currently facilitating the risk planning process with t…
