PMP practice question 28 of 35

A project requires a vendor to implement a technical, complex solution. The project team is concerned about selecting the optimal vendor to meet the needs of the project. What should the project manager do?

Full set: 230 questions

Domain Process

Answer options
A: Send requests for proposals to vendors used previously and assess their responses for relevance to the project.
B: Weigh all of the requests for demonstrations responses and select a vendor with the highest score.
C: Gather data through requests for information and check for relevance to industry expertise and project objectives. Correct answer
D: Review the data from the requests for quotations to find the lowest price to deliver the solution.
Correct Answer:
C. Gather data through requests for information and check for relevance to industry expertise and project objectives.
Explanation

When procuring a technical and complex solution, the project team must first understand market capabilities and identify qualified vendors. A Request for Information (RFI) is the appropriate procurement document used to gather data from potential sellers about their products, services, and industry expertise. Because the solution is complex, selecting a vendor based solely on past relationships or the lowest price introduces significant risk and may fail to meet project objectives. An RFI allows the project manager to screen vendors for the necessary technical acumen and alignment with project goals before proceeding to a more formal Request for Proposal (RFP) phase, ensuring only highly qualified vendors are considered for the final selection.

Why Incorrect

A: Restricting proposals only to previously used vendors limits the talent pool and may exclude the most qualified experts needed for a novel, complex technical solution. B: A "request for demonstrations" is not a standard initial procurement document. Demonstrations are typically part of the later evaluation phases of an RFP, not the initial discovery process. D: A Request for Quotation (RFQ) and selecting the lowest price is suitable for standardized or commoditized items, not for highly technical, complex solutions requiring specialized expertise.

References

1. Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 12.1.3.3 Procurement Documentation, p. 477. (Defines RFI, RFP, and RFQ, explicitly stating RFIs are used when more information on goods/services is needed from sellers).

2. Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). Section 2.8.4.1 Procurement, p. 75. (Discusses the use of RFIs for gathering market intelligence and vendor capabilities).

3. Project Management Institute (PMI). (2016). Software Extension to the PMBOK® Guide Fifth Edition. Section 12.1 Plan Procurement Management, pp. 215-216. (Highlights the necessity of evaluating technical expertise over cost for complex software/technical solutions).