PMP practice question 29 of 35
During execution, your team uncovers a technical risk that could require significant rework if it materializes. A senior engineer proposes a…
Full set: 230 questionsDomain Process
According to PMI principles, project managers must proactively manage risks and use data-driven techniques like Expected Monetary Value (EMV) to evaluate risk responses. The EMV of the current risk exposure is 240 hours (60% of 400), while the preventive action's EMV is 140 hours (80 hours + 15% of 400). Because the sponsor explicitly requested no scope additions without approval due to a tight budget, the project manager cannot unilaterally authorize the work. The correct approach is to quantify this cost-benefit trade-off and present the analysis to the sponsor. This facilitates an informed, transparent decision regarding the necessary budget and scope changes through the Perform Integrated Change Control process.
A: Bypasses the sponsor's explicit instructions regarding scope and budget changes, violating stakeholder engagement and integrated change control processes. C: Passively accepting the risk without presenting the highly cost-effective preventive option to the sponsor fails the project manager's duty to optimize project outcomes. D: Arbitrarily seeking a cheaper solution to bypass the sponsor's authority is unprofessional and violates the explicit requirement for sponsor approval on scope changes.
1. Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 11.4.2.2 Data Analysis (Expected Monetary Value analysis), pp. 435-436.
2. Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 4.6 Perform Integrated Change Control, pp. 113-115.
3. Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). Section 2.8 Measurement Performance Domain (Risk), pp. 122-127.
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1The project manager is preparing for the kickoff meeting of a project that follows a 'pla…
- Question 2Health Records Modernization at Hospital Case Study A project manager led a health record…
- Question 4A project manager is leading a project focused on developing a machine learning platform.…
- Question 5A project manager is leading an iterative project to develop a very innovative product. H…
- Question 6A team is using a predictive model to determine possible cost overrun scenarios for a dis…
- Question 7During the execution phase of a major infrastructure project, your team uncovers a signif…
