During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point…
Choose your answer, then check it against the explanation.
Domain Process
During the initial stage of a project, the team estimated activities for the next iteration in story
points. It was agreed that each story point would be assumed to be equal to one day of effort during
project execution. There are some activities estimated as two story points and others estimated as
100 story points.
What should the project manager ask the team to do next?
Question 7 of 35
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1In a daily standup meeting, a project manager notices that a team member's reports includ…
- Question 2In a geographically distributed team, a developer continues to delay a coding activity. T…
- Question 3A project manager has an engineering team mostly comprised of new hires. The project mana…
- Question 5A project manager is part of an organization that is assessing the use of agile delivery …
- Question 6A project team is using a vendor solution. The project team has been notified that the ve…
- Question 8A project manager is leading a long-term project, executed in stages, to set up a complex…