In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager…

Choose your answer, then check it against the explanation.

Domain People

In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team. What should the project manager do?