A person is writing a document identifying the business need for a project and is including a description of the product created by the project. She includes a list of stakeholders and pre assigned resources. What is the role of this person on the project?

Full set: 650 questions
Answer options
A: The project manager for the project or a company functional manager
B: A member of the project management team working at the direction of the project manager
C: The sponsor or the project manager Correct answer
D: A manager or executive in the organization who is higher in the corporate hierarchy than the project manager
Correct Answer:
C. The sponsor or the project manager