PPM-001 practice question 18 of 35

What are the performance measurements for the Schedule Control process?

Full set: 650 questions
Answer options
A: SV (EV - PV) and SPI (EV ÷ PV) Correct answer
B: SV (PV - EV) and SPI (PV ÷ EV)
C: SV (EV - BAC) and SPI (EV ÷ BAC)
D: SV (EV - AC) and SPI (EV ÷ AC)
Correct Answer:
A. SV (EV - PV) and SPI (EV ÷ PV)
Explanation

Schedule variance is (EV - PV) and schedule performance index is (EV ÷ PV).