PROJECT-PLANNING-DESIGN practice question 17 of 35

A divisional cost breakdown method of cost estimating has which of the following advantages over a cost per square foot method of cost estimating?

Full set: 100 questions
Answer options
A: It provides a quick reference or check at the early design stages.
B: It provides a simple method to calculate costs.
C: It is useful throughout design and construction of the project.
D: It is useful for generic buildings.
Correct Answer:
C