PROJECT-PLANNING-DESIGN practice question 32 of 35

For a government-owned project, architects can reduce consumption and waste by including which of the following requirements in their design and specifications? Check the four that apply.

Full set: 100 questions
Answer options
A: Construction waste recycling
B: Use of local materials
C: Means of construction
D: Reuse of existing structures
E: Limit bidding to local contractors
F: Use of low flow fixtures
Correct Answer:
A, B, D, F