PSD practice question 24 of 25
Select three criteria for the definition of done
Full set: 163 questionsCorrect Answer:
A. Code review is done; B. Acceptance tests pass; C. Regression tests pass
Explanation
Releasing the product at the end of the sprint doesn't relate to one item and when it's done. Code coverage does, but it's the worst criteria in this list, because it's a stimulus to write tests that cover a lot of lines rather than cover the functionality.
Keep practicing
Take the free PSD practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSD practice questions
- Question 1The developers can invite experts to the sprint planning to give them advice
- Question 2Database design must be complete before coding starts to ensure a solid foundation
- Question 3True or False: A Sprint can be canceled before the timebox ends.
- Question 4True or False: Best Practices are recommended to solve complex problems.
- Question 5True or False: Stakeholders can be included in Product Backlog refinement.
- Question 6If multiple teams are working on the same product, each team should have its own product …