PSD practice question 19 of 25

When using Scrum, can a Scrum Team use Continuous Delivery? (choose the best answer)

Full set: 163 questions
Answer options
A: No, because the increment has to be approved at the Sprint Review before it can be released, and a 2-week Sprint would not be considered continuous.
B: No, because stakeholders may have already seen the new features and the Sprint Review will be meaningless.
C: No, because before releasing an Increment it first has to fulfill the Definition of Done.
D: No, because the Product Owner may not be available each time a PBI is done, and the Product Owner has to decide if it should be released.
E: Yes, there is nothing in Scrum that conflicts with Continuous Delivery. Correct answer
Correct Answer:
E. Yes, there is nothing in Scrum that conflicts with Continuous Delivery.
Explanation

Scrum is compatible with Continuous Delivery as long as each Increment meets the Definition of Done. Continuous Delivery aligns with Agile principles, allowing frequent releases.