Scrum Teams using Kanban can start to increase predictability by: (choose the best answer)
Full set: 73 questionsCorrect Answer:
D. Reducing the amount of work in progress by introducing Work in Progress (WIP)
Limits.
Explanation
Scrum Teams using Kanban can start to increase predictability by reducing the amount of work in progress (WIP) through WIP limits. This approach helps to limit the number of items being worked on at any given time, thus reducing multitasking and context switching. It allows the team to focus on completing a few items before starting new ones, which directly impacts the flow of work and helps to predict when items will be completed. By controlling the WIP, teams can achieve a steady flow of work, improve cycle times, and make more reliable forecasts about future deliveries
Keep practicing
Take the free PSK-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSK-I practice questions
- Question 1What qualitative information can you get from a Cycle Time Scatterplot? (choose the best …
- Question 3What might a Scrum Team visualize with Kanban? (choose the best three answers)
- Question 4What is a probabilistic forecast intended to communicate? (choose the best answer)
- Question 5In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Li…
- Question 6Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urge…
- Question 7What is the best use for the Work Item Aging metric? (Choose the best two answers)