PSK-I practice question 7 of 15

What is the best use for the Work Item Aging metric? (Choose the best two answers)

Full set: 73 questions
Answer options
A: To influence the Scrum Team’s SLE.
B: To help the Developers inspect and adapt their Sprint in the Daily Scrum.
C: As a leading indicator to the length of the feedback loop for that Work Item.
D: As an indicator of the Work Item size.
E: To help the Scrum Team inspect and adapt their process and Definition of Workflow in their Retrospective.
Correct Answer:
BC
Explanation

Work Item Aging is an essential metric that helps the Scrum Team monitor progress and detect potential delays early. It is especially useful in Daily Scrums to identify items that are taking longer than expected, allowing the team to take corrective actions and prevent delays. It also serves as a leading indicator of how long the feedback loop for a Work Item may take.