PSK-I practice question 8 of 15

In the context of Scrum, which of the following statements about Cycle Time are true? (Choose the best two answers)

Full set: 73 questions
Answer options
A: Cycle Time should be exactly the length of a Sprint.
B: Cycle Time for some Product Backlog items might be longer than a length of Sprint.
C: Average Cycle Time should be shorter than a length of Sprint.
Correct Answer:
BC
Explanation

Cycle Time measures the time taken to complete individual work items, and while some items might take longer than a Sprint, on average, teams aim to have Cycle Times shorter than the Sprint duration to ensure a smooth flow and regular delivery of value. Reference: The Kanban Guide for Scrum Teams​​.