In the context of Scrum, which of the following statements about Cycle Time are true? (Choose the best two answers)
Full set: 73 questionsCorrect Answer:
BC
Explanation
Cycle Time measures the time taken to complete individual work items, and while some items might take longer than a Sprint, on average, teams aim to have Cycle Times shorter than the Sprint duration to ensure a smooth flow and regular delivery of value. Reference: The Kanban Guide for Scrum Teams.
Keep practicing
Take the free PSK-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSK-I practice questions
- Question 1What qualitative information can you get from a Cycle Time Scatterplot? (choose the best …
- Question 2Scrum Teams using Kanban can start to increase predictability by: (choose the best answer)
- Question 3What might a Scrum Team visualize with Kanban? (choose the best three answers)
- Question 4What is a probabilistic forecast intended to communicate? (choose the best answer)
- Question 5In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Li…
- Question 6Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urge…