PSK-I practice question 10 of 15
True or False: Little's Law is used to forecast a Scrum Team's output.
Full set: 73 questionsLittle's Law establishes a relationship between three flow metrics: Work in Progress (WIP), Cycle Time, and Throughput. It provides insights into how changes in one metric affect the others in a stable system. Little's Law is used to understand and manage flow within a system but is not a forecasting tool for output or future performance. It assumes a stable and predictable system where the input and output rates are consistent. Why Not True? Forecasting requires variability, historical data, and often different statistical models. While Little's Law supports system predictability and capacity planning, it does not directly project future Scrum Team outputs or delivery dates. Thus, Little's Law helps teams analyze and optimize flow but is not used for forecasting.
Keep practicing
Take the free PSK-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSK-I practice questions
- Question 1What qualitative information can you get from a Cycle Time Scatterplot? (choose the best …
- Question 2Scrum Teams using Kanban can start to increase predictability by: (choose the best answer)
- Question 3What might a Scrum Team visualize with Kanban? (choose the best three answers)
- Question 4What is a probabilistic forecast intended to communicate? (choose the best answer)
- Question 5In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Li…
- Question 6Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urge…