PSK-I practice question 14 of 15
True or False: The Scrum framework already contains elements that create a pull system.
Full set: 73 questionsCorrect Answer:
A. True
Explanation
The Scrum framework already contains elements that create a pull system. In Scrum, the team members "pull" work into the Sprint Backlog during Sprint Planning. They decide which Product Backlog items they will commit to completing based on their capacity and the Sprint Goal. This is a form of a pull system where the team only takes in as much work as they believe they can complete within a Sprint, aligning with Kanban principles that limit Work in Progress (WIP) to optimize flow
Keep practicing
Take the free PSK-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSK-I practice questions
- Question 1What qualitative information can you get from a Cycle Time Scatterplot? (choose the best …
- Question 2Scrum Teams using Kanban can start to increase predictability by: (choose the best answer)
- Question 3What might a Scrum Team visualize with Kanban? (choose the best three answers)
- Question 4What is a probabilistic forecast intended to communicate? (choose the best answer)
- Question 5In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Li…
- Question 6Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urge…