RCDDV14.1 practice question 29 of 35

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

Full set: 320 questions
Answer options
A: The component has released resources to meet program objectives
B: The component has met the quality requirements to meet program objectives Correct answer
C: The component has met the schedule requirements to meet program objectives
D: The component has met the benefits realization criteria to meet program objectives
Correct Answer:
B. The component has met the quality requirements to meet program objectives
Explanation

Before closing a program component, the program manager must verify that it has successfully produced its intended outputs and deliverables according to the pre-defined acceptance criteria. This primarily involves confirming that all quality requirements have been met, ensuring the component's deliverables are fit for purpose and can be integrated to contribute to the program's overall objectives and benefits. Closure is contingent on the successful completion and acceptance of the component's work, for which quality is a critical measure.

Why Incorrect

A. Releasing resources is a consequence of component closure, not a prerequisite for authorizing it.
C. While schedule performance is important, a component can be closed even if it is late, as long as its work is complete and accepted.
D. Benefits are typically realized at the program level after component outputs are integrated; a single component's closure is not usually tied to benefits realization.

References

1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.4.5, Program Component Transition and Closure, pp. 90-91. (Discusses verifying that component deliverables meet acceptance criteria before closure).

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 4.7, Close Project or Phase, p. 123. (Highlights verifying that all project work is complete and deliverables are accepted as a key activity).