RCDDV14.1 practice question 34 of 35

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate reviews. What should the program manager do next?

Full set: 320 questions
Answer options
A: Ask the stakeholders what they want and proceed with their recommendations
B: Agree with the customer and Initiate change control procedures
C: Continue periodic gate reviews to maintain program effectiveness for benefits realization Correct answer
D: Replace program reviews with periodic communications of the program's status
Correct Answer:
C. Continue periodic gate reviews to maintain program effectiveness for benefits realization
Explanation

Phase gate reviews are a fundamental component of effective program governance. Their purpose is to provide formal decision points where the governance board assesses program health, revalidates the business case, and authorizes progression to the next phase. Eliminating this critical oversight mechanism, even when performance is good, introduces significant risk. The program manager has a responsibility to uphold the established governance framework and should explain the continued value of these reviews for maintaining alignment, managing risk, and ensuring the ongoing realization of benefits.

Why Incorrect

A. While stakeholder input is valuable, the program manager must prioritize the integrity of the governance process over a single stakeholder's preference.
B. Agreeing to remove a key governance control is irresponsible. The change control process should be used to implement sound decisions, not to weaken program oversight.
D. Status communications are informational and do not replace the formal decision-making function of a gate review. A review is an active assessment, not a passive report.

References

1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.4.3, Phase-Gate Reviews. This section defines phase-gate reviews as formal governance activities and decision points essential for program control.

2. Cooper, R. G. (2008). Perspective: The Stage-Gate® Idea-to-Launch Process—Update, What's New, and NexGen Systems. Journal of Product Innovation Management, 25(3), 213-232. https://doi.org/10.1111/j.1540-5885.2008.00296.x. This academic article highlights the critical role of gate reviews in governance and decision-making for complex initiatives.