Mark is the Product Owner and he asks you, the Scrum Master what burndown charts actually track. What's the best response for Mark?

Full set: 148 questions

Domain Initiate Phase

Answer options
A: Burndown charts will track the remaining work across the project time. Correct answer
B: Burndown charts will track the value of the work performed by the Development Team.
C: Burndown charts will track work still left in the project.
D: Burndown charts will track the cost of the work.
Correct Answer:
A. Burndown charts will track the remaining work across the project time.
Explanation

A burndown chart is a tool used to visualize the amount of work remaining against time. The vertical axis represents the work left to be done (typically in story points or hours), and the horizontal axis represents time (days of a Sprint or Sprints in a release). It provides a clear graphical representation of progress, helping the team track if they are on schedule to complete the planned work.

Why Incorrect

B. Burndown charts track remaining work effort, not the business value of the work performed.
C. This is partially correct, but option A is more precise by including the essential dimension of time.
D. Burndown charts track remaining work, not the financial cost of the work.

References

A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition, SCRUMstudy, 2017. Chapter 8, Section 8.6, "Update Burndown Chart," describes it as a graph showing "the amount of remaining work in a Sprint on a day-to-day basis."

Stray, V., Sjøberg, D. I., & Dybå, T. (2016). The daily stand-up meeting: A grounded theory study. Journal of Systems and Software, 114, 101-124. https://doi.org/10.1016/j.jss.2016.01.004 (This paper discusses the use of burndown charts as a key information radiator for tracking progress discussed in stand-ups).

Scroll to Top