SMC practice question 23 of 25

You are the Scrum Master for the ID7 Project for your organization. Martha is serving as the Product Owner for this project. Martha meets with you and asks for your advice on how she should go about estimating the work in the Product Backlog. What should you tell Martha?

Full set: 148 questions

Domain Plan and Estimate Phase

Answer options
A: The Development Team will work with Martha to estimate the items in the Product Backlog with story points. Correct answer
B: The Development Team will work with you, the Scrum Master, to create time and cost estimates for all the Product Backlog items.
C: Martha can estimate the items in the Product Backlog, but you, the Scrum Master, must be approve the estimates prior to each Sprint Planning meeting.
D: Martha can estimate the items in the Product Backlog, but the Development Team must approve the estimates prior to the Sprint beginning.
Correct Answer:
A. The Development Team will work with Martha to estimate the items in the Product Backlog with story points.
Explanation

In Scrum, the people who will be doing the work are responsible for estimating the effort. Therefore, the Development Team (referred to as the Scrum Team in the SBOK® Guide) estimates the Product Backlog Items. The Product Owner (Martha) is responsible for clarifying the items and answering any questions the team has to ensure a clear understanding, but she does not provide the estimates. The Scrum Master facilitates the estimation process but does not participate in estimating or approving the estimates.

Why Incorrect

B: The Development Team collaborates with the Product Owner for clarification on items, not the Scrum Master. C: The Product Owner does not estimate the work, and the Scrum Master does not approve estimates; this violates the team's self-organization. D: The Development Team creates the estimates based on their expertise; they do not simply approve estimates created by the Product Owner.

References

A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition, SCRUMstudy. Chapter 6, Section 6.4, "Estimate User Stories", page 128. It states, "The Scrum Team decides on the effort required to complete each User Story, and the Scrum Master facilitates this process." The "Scrum Team" here refers to the cross-functional team performing the development work.