SMC practice question 23 of 25
You are the Scrum Master for the ID7 Project for your organization. Martha is serving as the Product Owner for this project. Martha meets with you and asks for your advice on how she should go about estimating the work in the Product Backlog. What should you tell Martha?
Full set: 148 questionsDomain Plan and Estimate Phase
In Scrum, the people who will be doing the work are responsible for estimating the effort. Therefore, the Development Team (referred to as the Scrum Team in the SBOK® Guide) estimates the Product Backlog Items. The Product Owner (Martha) is responsible for clarifying the items and answering any questions the team has to ensure a clear understanding, but she does not provide the estimates. The Scrum Master facilitates the estimation process but does not participate in estimating or approving the estimates.
B: The Development Team collaborates with the Product Owner for clarification on items, not the Scrum Master. C: The Product Owner does not estimate the work, and the Scrum Master does not approve estimates; this violates the team's self-organization. D: The Development Team creates the estimates based on their expertise; they do not simply approve estimates created by the Product Owner.
A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition, SCRUMstudy. Chapter 6, Section 6.4, "Estimate User Stories", page 128. It states, "The Scrum Team decides on the effort required to complete each User Story, and the Scrum Master facilitates this process." The "Scrum Team" here refers to the cross-functional team performing the development work.
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…