How can labor units be updated for tasks in Primavera P6?
Full set: 429 questionsLabor units for tasks can be updated in Primavera P6 by adjusting them in the Resources tab within Activity Details. This method allows for precise modifications to resource allocations per activity.
B. Modifying the baseline directly does not change labor units associated with tasks.
C. The Team Usage Profile does not automatically update individual task labor units.
D. Highlighting labor-driven tasks in the Gantt chart does not facilitate updates to labor units.
1. Oracle Primavera P6 Documentation, Section on Resource Management, Page 125.
2. PMI’s A Guide to the Project Management Body of Knowledge (PMBOK), 6th Edition, Section 6.5 on resource management.
3. Primavera P6 Professional User Guide, Chapter 4 on Activity Details, Page 101.
4. Academic Publication on Project Management in Practice, DOI: https://doi.org/10.1080/01446193.2020.1725400.
Keep practicing
Take the free 1Z0-1129 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1129 practice questions
- Question 2What is the purpose of tracking utilization percentages in the Analysis Page?
- Question 3What two steps are required to create a baseline in Primavera P6?
- Question 4What two features does the Maintain Baselines tool offer?
- Question 5What two factors determine the choice of calendar for an activity?
- Question 6What is the purpose of drag-and-drop functionality in the WBS tab?
- Question 7What two actions are possible when using the drag-and-drop functionality in the WBS tab?